Installing the operator control box in the shelter. To install the operator control box in the shelter,
open the operator control box cover (1) on the top of the heater.
Unwind the 25-foot control cable (2) to gain access to the operator control panel.
Remove the operator control box (3) from its stowage location by releasing the single turn-key latch (4)
and lifting upward.
Slide the operator control box (3) and attached cable (2) under the side of the shelter in a convenient
location that will not hinder entry or exit from the shelter or act as a trip hazard. Take care not to get any
dirt or debris on the operator control box.
Hang the operator control box (3) inside the shelter at a height of three to six feet using the attached
cable (5). Place the operator control box (3) in a location that is not in the direct path of air coming from
the heated air outlet duct or in the direct path of cold air entering from the shelter entry.