TM 9-2540-205-24& P
VOLTAGE REGULATOR ASSEMBLY - STEWART-WARNER 10560C24, 10560G
This task covers:
a. Removal
b. Installation
INITIAL SETUP
Tools
Personnel Required
Tool Kit, Mechanics Gen (Item 1, Appendix B)
63G
Equipment Condition
Blower assembly removed (page 3-99)
LOCATION
ITEM
ACTION
REMARKS
REMOVAL
NOTE
Tag all wires and terminals to aid during installation (page 2-3).
1. Motor mounting bracket (1)
Lead (2)
2. Blower assembly (3) and
Two screw assemblies (5)
voltage regulator assembly (4)
3. Blower assembly (3)
Voltage regulator assembly (4)
INSTALLATION
4. Blower assembly (3)
Voltage regulator assembly (4)
5. Blower assembly (3) and
Two screw assemblies (5)
voltage regulator assembly (4)
6. Motor mounting bracket (1)
Lead (2)
Remove.
Unscrew and remove.
Remove.
Install.
Install.
Install.
3-114