T M 9 - 4 9 3 1 - 3 8 1 - 1 4 & P - 2
2-11. Electrical Load Bank A5.
Task
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
Title
Remove Electrical Load Bank A5
Remove Panel Connector Bracket
Remove Receptacle Connector Body A5J1, A5J2, or A5J3
Repair Connector A5J1, A5J2, or A5J3
Remove Cover
Remove Circuit Card Assembly TB1 or Terminal Board
Assembly TB2
Repair Circuit Card Assembly TB1 or Terminal Board
Assembly TB2
Replace Electrical Components: Resistors, Relays, and
Capacitor
Replace Terminal Lug E1, E2, E4, E5, E6, or E7 and
Electrical-Mechanical Post
Replace Terminal Stud E3, E8, or E9
Replace Butt Hinge
Install Circuit Card Assembly TB1 or Terminal Board
Assembly TB2
InstalI Cover
Install Receptacle Connector Body A5J1, A5J2, or A5J3
InstalI Panel Connector Bracket
Install Electrical Load Bank A5
Frames
1
2
3
4
5
6
7
8 - 1 3
1 4 - 1 5
16
17
18
19
20
21
22
TASK 1. Remove Electrical Load Bank A5.
Applicability: All Models
Common Tools:
Screwdriver, cross tip, No. 2
Special Tools: None
Supplies: None
Personnel: One
Equipment Condition:
Thermal system test controller on a clean work surface.
Preliminary Procedures:
1. Remove thermal system test controller case cover; refer to volume 1, para. 4-17.
2. Remove thermal system test controller; refer to para. 2-5, task 2.