T M 9 - 4 9 3 1 - 3 8 1 - 1 4 & P - 2
FRAME 16
NOTE
Use this task to replace any of three terminals E3, E8,
or E9. Terminal E9 is shown.
Read paragraph 2-4 on tagging and soldering wires
before doing any work.
Remove Terminal Stud:
1.
Tag and unsolder and takeoff wire (1) from terminal E9 (2) with pliers.
2.
Unscrew and take out machine screw (3), lockwasher (4), and flat washer (5) with
screwdriver and wrench. Turn in terminal (2) and get rid of lockwasher (4).
Install Terminal:
3.
Line up hole in new terminal (2) with hole in chassis (6).
4. Screw in screw (3), new Iockwasher (4), and washer (5) with screwdriver and wrench.
5.
Using torque screwdriver and bit, torque screw (3) between 6 and 7 pound-inches
(0.68 and 0.79 Newton meter) with handle, extension, and bit.
6.
Solder wire (1) to terminal (2).
Follow-on Maintenance:
1. Install electrical load bank A5; refer to task 16.
2. Install thermal system test controller; refer to para. 2-5, task 8.
3. Install thermal system test controller case cover; refer to volume 1, para. 4-18.
TASK 10 ENDS HERE
Volume IV
Para. 2-11, Task 10
2-305