Install Circuit Breaker:
1.
Put new circuit breaker (1) through hole in pad
2.
Screw on and tighten nut (3), Iockwasher (4), and
socket.
assembly (2).
rubber ring (5) with handle and
3.
Screw in and tighten mounting screw (6) with screwdriver.
4.
Put screw (7) through loops in wires (8) and screw into circuit breaker terminal (9)
with screwdriver.
Follow-on Maintenance:
1. install panel assembly A1; refer to task 26.
2. Install thermal system test controller; refer to para. 2-5, task 8.
3. install thermal system test controller case cover; refer to volume 1, para. 4-18.
TASK 16 ENDS HERE