Install Cover:
1.
Line up holes in cover (1) with holes in electrical-mechanical posts (2).
2.
Screw in and tighten four machine screws (3), new lockwashers (4), and flat washers
(5) with screwdriver.
3.
Using torque screwdriver and bit, torque screws (3) between 5 and 6 pound-inches
(0.57 and 0.68 Newton meter).
Follow-on Maintenance:
1. Install electrical load bank A5; refer to task 16.
2. lnstaIl thermal system test controller case; refer to para. 2-5, task 8.
3. Install thermal system test controller case cover; refer to volume 1, para. 4-18.
TASK 13 ENDS HERE
Volume IV
Para. 2-11, Task 13
2-311